Network Rail completes £3m Derwent Valley Line track renewal after nine-day closure
Trains returned between Derby and Matlock on 23 November after Network Rail renewed track at Matlock Bath, Cromford and Whatstandwell in a single blockade it said replaced eight weekend possessions.

Network Rail has reopened the Derwent Valley Line in Derbyshire after a nine-day closure between Derby and Matlock in which it renewed track at Matlock Bath, Cromford and near Whatstandwell station at a cost of £3m.
Services resumed on the morning of Monday 23 November, the infrastructure owner said. According to its completion release, engineers installed 4.6km of new rail, 3,509 sleepers and 6,400 tonnes of ballast, replacing equipment that had reached the end of its working life.
Network Rail said the renewal would make the line more resilient, cut the need for future maintenance and reduce the risk of delays caused by track faults.
Eric Larocque, Network Rail operations director, said: "We know closing the railway for nine days caused disruption, but it allowed our teams to complete a substantial amount of essential work safely and efficiently – avoiding what would have otherwise involved eight weekend closures."
The work
Eight engineering trains were used during the blockade, Network Rail said, including a New Track Construction train that lays rails and sleepers as it travels along the line. The company said this allowed its teams to renew a significant amount of track within the closure.
The scope matched what Network Rail set out when it first announced the closure on 16 October, when it said rail, sleepers and ballast that had reached the end of their working life would be replaced to improve the resilience of the East Midlands route and reduce unplanned maintenance.
Earlier Network Rail notices described the job as renewing more than 4.5km of track, while the completion release gives 4.6km of new rail.
Passenger arrangements
Rail replacement buses ran between Derby and Matlock from Saturday 14 to Sunday 22 November. Network Rail issued a reminder on 9 November and warned that some replacement bus stops were some distance from the relevant station. Services between Derby and Sheffield via Chesterfield were unaffected, it said.
East Midlands Railway (EMR), which is operated by Transport UK, published its own advice on 2 November. The operator said its Intercity services between Sheffield, Derby and London were not affected by the engineering work and that all replacement buses would be fully accessible.
Philippa Cresswell, customer experience director at East Midlands Railway, said: "We'd like to thank our customers for their patience and understanding while this vital work takes place."
The route
According to the Derwent Valley Line Community Rail Partnership, EMR runs an hourly service on the line with a typical journey time of 34 minutes between Derby and Matlock. The same trains continue to Nottingham, Newark and Lincoln.
The partnership said the line passes through the Derwent Valley Mills World Heritage Site between Derby and Matlock Bath.
Before the closure began, Larocque said the investment would help Network Rail provide a safer, more reliable railway for passengers and freight operators. The completion release said the renewed track would support smoother, more reliable journeys for passengers and freight for years to come.
Network Rail said the nine-day possession replaced what would otherwise have been eight separate weekend closures of the line.
Sources
- Network Rail (opens in a new tab) (accessed 2026-11-23)
- Network Rail (opens in a new tab) (accessed 2026-11-23)
- Network Rail (opens in a new tab) (accessed 2026-11-23)
- East Midlands Railway (opens in a new tab) (accessed 2026-11-23)
- Derwent Valley Line Community Rail Partnership (opens in a new tab) (accessed 2026-11-23)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.