Network Rail to close Brighton Main Line for a day ahead of nine-day February blockade

Engineers will install more than 700 metres of new rail at Brighton and prepare for conductor rail renewal when the route shuts between Three Bridges and Brighton on Sunday 29 November.

Rail engineers working on track during a railway line closure
Photo: Network Rail

Network Rail will close the Brighton Main Line between Three Bridges and Brighton on Sunday 29 November 2026 for a day of track, earthworks and inspection work, ahead of a nine-day shutdown in February 2027.

Buses will replace Southern and Thameslink trains for the day and journeys will take longer, Network Rail and the train operators said in a joint announcement on 20 November. National Rail Enquiries lists the work as closing all lines between Three Bridges and Brighton.

The route will then shut for a further nine days from Saturday 13 to Sunday 21 February 2027, during the February half term.

Lucy McAuliffe, Network Rail's Sussex route director, said: "This work is vital to reduce faults, improve journey reliability and keep services running safely for years to come."

The 29 November work

Engineers will install more than 700 metres of new rail at Brighton, Network Rail said. Between Three Bridges and the Ouse Valley Viaduct they will maintain track, signalling equipment and points, and clear overgrown vegetation.

Earthworks teams will examine embankments and cuttings, including at Burgess Hill, and renew and stabilise the Stonehall cutting. The day also includes condition checks on tunnels, including Haywards Heath Tunnel, and inspections of bridges, including those on the M23 and Haywards Heath Road.

Network Rail said engineers will also carry out preparatory work for the new conductor rail to be installed during the February closure. Its project page explains that the conductor rail, also known as the third rail, supplies power to trains.

The February programme

Network Rail first announced the 13 to 21 February 2027 dates on 26 March 2026. According to its 10 November 2026 release, the February scope includes new rails at Plumpton and Preston Park, renewed track and switches and crossings at Keymer Junction near Wivelsfield, and new conductor rail between the Clayton Tunnel and Preston Park.

The March 2026 release had described the track element differently, listing new rails at Plumpton and Haywards Heath and switches and crossings at Preston Park, and said the programme would include essential maintenance on the Ouse Valley Viaduct.

The November release also lists strengthening and stabilisation at Haywards Heath cutting and the Balcombe Stamford rock cutting, structural works at Balcombe Tunnel, new rails through the Clayton Tunnel, and new signalling and renewal of the level crossings at Spatham Lane near Westmeston and at Hamsey in East Sussex.

Network Rail's project page says the wider programme covers track renewal, earthworks, drainage repairs, bridge maintenance and improved access points, and has been timed to coincide with most schools' half-term holidays.

McAuliffe said the one-day shutdown and the February closure "allows us to deliver a huge volume of work at once, avoiding repeated disruption across multiple weekends or during the busy summer season."

Redhill at Christmas

Network Rail said engineering work will also take place in the Redhill area over Christmas 2026 and New Year 2027 as part of the ongoing Brighton Main Line investment. Buses will replace services through Redhill station from Sunday 20 December, with disruption continuing up to and including Sunday 3 January 2027, while engineers install new switches and crossings along more than a mile of railway.

That work is part of a £31.7m Network Rail investment across the Southern region's network over Christmas 2026, according to the Redhill announcement. Network Rail has not given a cost figure for the 29 November or February closures.

The route has been through a comparable blockade before. In 2019 Network Rail reopened the line after a £67m, nine-day programme that replaced thousands of metres of conductor rail at Folly Hill and included work in the Balcombe, Clayton, Patcham and Haywards Heath tunnels. At the time it said the Brighton Main Line carries 300,000 passengers on a normal weekday.

Passenger arrangements

On 29 November direct Southern trains between London Victoria and Brighton will be diverted via Horsham, Littlehampton and Hove with extended journey times. Southern tickets will be accepted on Southeastern trains between Hastings and London at no extra cost, and a reduced Thameslink service will run between Gatwick Airport and Three Bridges.

In February, customers travelling between the Brighton and Hove areas and Gatwick Airport or London are encouraged to use the diverted train service rather than replacement buses. Bus routes will include Three Bridges to Brighton via all stations, Three Bridges to Lewes via Haywards Heath and Cooksbridge, Three Bridges to Haywards Heath, Haywards Heath to Plumpton, and Lewes to East Grinstead on weekdays only.

Jenny Saunders, Southern, Gatwick Express and Thameslink Customer Service Director, said the closures are crucial to keeping services reliable and encouraged customers to plan ahead, particularly for the February week, when some may find it easier to work flexibly.

Online journey planners will begin showing revised train and replacement bus times for the February week later in November 2026, Network Rail said.

Sources

  1. Network Rail (opens in a new tab) (accessed 2026-11-21)
  2. Network Rail (opens in a new tab) (accessed 2026-11-21)
  3. Network Rail (opens in a new tab) (accessed 2026-11-21)
  4. Network Rail (opens in a new tab) (accessed 2026-11-21)
  5. Network Rail (opens in a new tab) (accessed 2026-11-21)
  6. Network Rail (opens in a new tab) (accessed 2026-11-21)
  7. National Rail Enquiries (Rail Delivery Group) (opens in a new tab) (accessed 2026-11-21)

This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.

Get stories like this every Friday

The Rail Construction Today weekly: the week's railway infrastructure and construction news in one email, free, and the TC Media Group monthly edition. Unsubscribe in one click.

By subscribing you agree to receive the Rail Construction Today weekly and the TC Media Group monthly edition. We confirm your address first. Privacy.

More from Rail Construction Today