GBR Anglia puts £2m into c2c route recovery after months of disruption

Night-time tamping between Upminster and Benfleet in December is intended to lift the last heat-related speed restrictions on the Essex Thameside line before the new timetable starts on 13 December.

Key figures: £2m Additional investment; 8,000 Ballast used to date; 13 Target for lifting last speed restrictions; 4.5% Period 7 cancellations (c2c)
Graphic: Rail Construction Today
A track tamping machine working on a railway line at night
Photo: GBR Anglia

GBR Anglia is spending a further £2m on the c2c route after months of delays and cancellations, and aims to lift the last speed restrictions before the new timetable on 13 December.

The body, which brings c2c, Greater Anglia and Network Rail Anglia together under one structure, announced the investment on 26 November. It said the driest summer in 50 years had dried and shrunk the clay soil under the track between London Fenchurch Street and south Essex, forcing temporary speed restrictions to keep trains running safely.

Signalling and power supply failures, a fire in Stratford in August and the freight train derailment at Barking in October added to the disruption, GBR Anglia said.

Martin Beable, Chief Operating Officer for GBR Anglia, said: "We’re really sorry to all our c2c customers who have experienced delays and cancellations over recent months during a very challenging period."

The recovery programme

A Thameside Recovery Programme team has been set up to carry out enhanced maintenance, engineering and operational improvements across the route, according to GBR Anglia. More than 8,000 tonnes of ballast have already gone into the track to improve stability, and enhanced track treatment has removed some restrictions.

The remaining restrictions cannot simply be lifted now the summer is over, GBR Anglia said, because winter rain makes the shrunken clay track bed swell. A tamping machine will therefore work nights through December to stabilise the track, with the intention of removing the last restrictions before 13 December.

Beable said: "We know saying 'sorry' isn't enough. We need to regain the trust of our customers by providing a reliable train service they can depend on."

Part of the £2m is going into the route's power supply infrastructure, including fault detection and the response when faults occur, GBR Anglia said. It has also put extra staff on stations, quadrupled the frequency of deep cleaning on the c2c fleet and plans further station spending over the coming year. Further work is planned through 2027 as part of a long-term resilience programme for the Thameside route.

Performance figures

c2c's own performance page sets out the scale of the problem. In Period 7, from 20 September to 17 October, the operator recorded cancellations of 4.5% against a target of 1.60%, and On Time to 3 of 84% against a target of 89.80%.

Period 7 measure Actual Target
Cancellations 4.5% 1.60%
On Time to 3 84% 89.80%

c2c attributed most of its On Time to 3 failures to Soil Moisture Deficit speed restrictions, with a blanket 50mph limit between Leigh on Sea and Pitsea causing most delays. A signalling incident on 8 October led to 81 cancellations, it said.

The operator's commentary is more cautious than the November release on timing. c2c said a substantial recovery was unlikely until the Restrictions of Use were lifted and that an elevated risk of cancellations was expected to remain until February 2027.

Barking repairs

The Barking incident was the derailment of a GB Rail freight train on 23 October, Network Rail said. Engineers carried out emergency repairs to more than 1.2km of track, rebuilt bespoke points that were damaged beyond repair and replaced severed signalling equipment and cabling. c2c passenger services between Barking and Dagenham Dock, Rainham and Purfleet resumed from 11 November.

Background

The integrated Anglia leadership team, described by Network Rail as a step towards the establishment of Great British Railways, was announced on 14 May 2026, with Jamie Burles as Managing Director and Beable as Chief Operating Officer. The May release referred to an integrated Anglia railway; the November release uses the name GBR Anglia.

c2c services between Fenchurch Street and Shoeburyness transferred to public ownership on 20 July 2025, according to the Department for Transport, making c2c the second operator brought in under the Public Ownership Act and the sixth run by the Department for Transport Operator.

December works

Track treatment trains will run for extended night hours between Upminster and Benfleet, affecting some late evening and early morning services. On 7 December the last train to Shoeburyness via Laindon leaves Liverpool Street at 21:52, with rail replacement buses from Upminster afterwards.

On 5 and 6 December buses will replace trains between Leigh-on-Sea and Shoeburyness for Access for All lift work at Chalkwell and Southend East. On Sunday 13 December the line between Upminster and Pitsea via Laindon will be closed for engineering work.

Sources

  1. Network Rail (GBR Anglia) (opens in a new tab) (accessed 2026-11-27)
  2. c2c (opens in a new tab) (accessed 2026-11-27)
  3. Network Rail (opens in a new tab) (accessed 2026-11-27)
  4. Network Rail (opens in a new tab) (accessed 2026-11-27)
  5. Department for Transport (GOV.UK) (opens in a new tab) (accessed 2026-11-27)

This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.

Get stories like this every Friday

The Rail Construction Today weekly: the week's railway infrastructure and construction news in one email, free, and the TC Media Group monthly edition. Unsubscribe in one click.

By subscribing you agree to receive the Rail Construction Today weekly and the TC Media Group monthly edition. We confirm your address first. Privacy.

More from Rail Construction Today