Manchester Airport station to shut on 6 December as £115m Kier remodelling starts
Network Rail will close the station for one day to install a utility bridge, the first job in a programme of platform extensions, junction remodelling and resignalling that runs to the middle of 2028.

Manchester Airport railway station will shut to trains on Sunday 6 December as Network Rail and its contractor Kier start a £115m remodelling that will lengthen three platforms and rebuild the junction on the approach.
Network Rail said the station would be closed throughout the Sunday and reopen as normal on Monday 7 December. It describes the possession as a 29-hour closure. Rail replacement buses will run and customer-handling teams will be on hand, it said.
During the closure engineers will install a new utility bridge across the railway to carry electrical cables. Network Rail said this would allow an existing bridge used by Manchester Airport Group to be removed at Easter 2027, with a new structure built later that year.
Simon Daly, Network Rail senior sponsor, said: "This work is an important first step in our £115 million investment and will help create more capacity, allow longer trains to serve the station and improve the reliability of journeys for years to come."
The contract
Kier announced on 8 October 2026 that Network Rail had awarded it a £54m contract to deliver the remodelling, a day after Network Rail first announced the £115m programme and said Kier would deliver the upgrades between then and 2028.
Kier said platforms one to three would be extended to accommodate two six-carriage trains per platform. Its works include new retaining walls, updated track and overhead power equipment, a reconstructed overbridge and upgraded signalling.
The contractor said its scope also covers reshaping the surrounding land, with embankment and cutting adjustments and new retaining structures to create space for the expanded layout, and diverting utilities to maintain station and airport operations throughout delivery.
Network Rail said the current railway layout limits how trains can move into and out of the station, and that the length of the existing platforms restricts the trains that can use them. The scope therefore includes remodelling the junction outside the station alongside the platform extensions and modernised signalling.
Lord Hendy, Rail Minister, said in October: "Manchester Airport is a vital transport hub and this £115 million investment from government" would deliver more reliable services and increase capacity. He added that the scheme "is the sort of improvement Great British Railways will be designed to deliver."
The closure programme
The 6 December possession is the first in a package of engineering work that Network Rail said would run from the end of 2026 to the middle of 2028. After it, there will be a number of weekend closures over 2027, which Network Rail said prepare for 10 weeks of upgrades at the start of 2028.
Manchester Airport itself will remain open during the railway closure, according to Network Rail. The infrastructure owner said it was working with Kier, Manchester Airport Group, Transport for Greater Manchester and train operators on the work.
Chris Nutton, Major Projects & TRU Director at TransPennine Express, said the operator was working with Network Rail and industry partners to minimise disruption, and encouraged customers to check their journeys before travelling.
Wider programme
The station scheme forms part of the Manchester Rail Upgrade, formerly the Manchester North West Transformation Project (MNTP). Network Rail said schemes already delivered under the programme include electrification between Wigan and Bolton, in service from summer 2025, and platform extensions at Mauldeth Road, Gatley and East Didsbury. Network Rail invested £8.5m in those airport-line platform extensions in January 2023.
Ongoing schemes include a third platform at Salford Crescent and new turnback sidings at Oldfield Road and Brewery Junction, with associated signalling and overhead line installation in Manchester.
The airport station's previous large upgrade was a fourth platform, with track and signalling work completed in February 2015 and the platform due into use in May that year.
The weekend closures through 2027 will lead into the 10-week block of work at the start of 2028.
On the record: Kier, Transport for Greater Manchester
Sources
- Network Rail (opens in a new tab) (accessed 2026-11-27)
- Network Rail (opens in a new tab) (accessed 2026-11-27)
- Network Rail (opens in a new tab) (accessed 2026-11-27)
- Kier (opens in a new tab) (accessed 2026-11-27)
- Network Rail (opens in a new tab) (accessed 2026-11-27)
- Network Rail (opens in a new tab) (accessed 2026-11-27)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.