Network Rail targets summer 2029 for Oxford station platform and western entrance

The next phase of the Oxford station upgrade would add a through platform and a western entrance, with Roger Dudman Way closing for around 20 months to build new bridges at Sheepwash.

Platforms and tracks at Oxford railway station
Photo: Network Rail

Network Rail is targeting summer 2029 to open a new through platform and a western entrance at Oxford station, subject to funding being released and the main construction contract being awarded, it said on 26 November 2026.

The announcement, issued by Network Rail's Wales & Western region for the Great Western route, sets out an indicative programme for the next phase of the station upgrade. Preparatory work is planned for early 2027, followed by construction of new bridges and the platform, with the western entrance scheduled across 2028 and 2029.

Network Rail said the improvements are intended to support potential future services linked to East West Rail, the reopening of the Cowley Branch Line and other developments in and around the city. Its Oxfordshire project page says the rail infrastructure around the station is near full capacity and cannot currently support the start of East West Rail services.

Tom Pierpoint, industry programme director for Network Rail's Great Western route, said the platform and entrance were an important part of preparing the station for the future, "giving passengers another way in and out of the station while creating the extra capacity needed to support more train services."

The construction programme

Under the indicative programme, Roger Dudman Way would close to through traffic for around 20 months. Pedestrian and cycle access would be maintained, and a diversion route would be put in place for vehicles needing local access.

The closure would allow teams to build new road and rail bridges at Sheepwash and divert utility pipes and cables. The plans include a road diversion to the north and a temporary footbridge to keep access to and from Roger Dudman Way. Network Rail's project page describes the work as replacing Sheepwash Bridge over Castle Mill Stream so it can carry an additional railway line, alongside a new Platform 5 and line.

Pierpoint said: "We know delivering the next phase of the upgrade will have an impact locally, particularly around Roger Dudman Way." Network Rail said it was working with its contractors and partners to shorten the closure, including carrying out some activities around the clock where appropriate, and would share details of piling and other construction activity once the programme is finalised.

Botley Road and its pedestrian walkways are expected to remain open throughout the remaining work, Network Rail said.

The western entrance

Design work on the western entrance has restarted and is being updated for the latest passenger forecasts, including travel associated with East West Rail and the Universal Resort in Bedfordshire. Network Rail expects the design to progress through the planning process by mid-2027.

Current proposals include ticket machines, ticket gates and toilets, with cycle parking and passenger pick-up and drop-off areas also under consideration.

The additional platform would provide capacity for potential future services, including East West Rail and possible services between Cowley and London Marylebone. Network Rail said no new train timetable was being announced as part of the update.

Background

Both elements were in the scope confirmed in August 2022, when the Department for Transport awarded £78.6m to Network Rail for the Oxford station and railway scheme. That scope included a new track and platform alongside the existing platform 4 and a western entrance next to Botley Road. The Oxford Local Enterprise Partnership (OxLEP) contributed a further £10.5m, and the award followed £69m of government investment the previous May. Kier was appointed as contractor for that earlier phase in 2022.

The earlier phase closed Botley Road beneath the railway bridge from April 2023 until it reopened to traffic on 20 September 2026. The 2022 release said the bridge works would lower the road so standard double-decker buses could pass underneath for the first time. Work on that stage is now being completed, including the temporary junction from Cripley Road to Roger Dudman Way, permanent railings and paving repairs in Frideswide Square, with a new southern walkway on Botley Road being built overnight.

On the demand side, East West Railway Company says freight and charter services on its first section between Oxford and Milton Keynes Central began at the end of 2025, and that the Transport Secretary named Chiltern Railways in March 2025 as operator of passenger services on that section. Its planned service pattern includes two Oxford to Milton Keynes services an hour in each direction.

In an announcement on 23 October 2025, the government said the Cowley Branch Line would reopen with new stations at Littlemore and Cowley. Oxfordshire County Council said £120m had been announced for the reopening, with stations at Oxford Cowley and Oxford Littlemore, and that the line is forecast to attract almost one million return journeys a year.

What happens next

Separate longer-term proposals for the station area include a potential eastern entrance, a cycle hub, better connections with other transport and improvements to public spaces. Oxford City Council's station masterplan, covering the station site and car park, is separate to but complements Network Rail's capacity works.

Network Rail said public consultation on the wider proposals is provisionally planned for late May to early July 2027, with regular stakeholder update sessions to be held during 2027.

Map of the UK and Ireland with a marker at Oxford station, South East
Oxford station, South East. Map: Rail Construction Today. Map credits

Sources

  1. Network Rail (opens in a new tab) (accessed 2026-11-27)
  2. Network Rail (opens in a new tab) (accessed 2026-11-27)
  3. Network Rail (opens in a new tab) (accessed 2026-11-27)
  4. Network Rail (opens in a new tab) (accessed 2026-11-27)
  5. East West Railway Company (opens in a new tab) (accessed 2026-11-27)
  6. HM Treasury / GOV.UK (opens in a new tab) (accessed 2026-11-27)
  7. Oxfordshire County Council (opens in a new tab) (accessed 2026-11-27)
  8. Oxford City Council (opens in a new tab) (accessed 2026-11-27)

This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.

Get stories like this every Friday

The Rail Construction Today weekly: the week's railway infrastructure and construction news in one email, free, and the TC Media Group monthly edition. Unsubscribe in one click.

By subscribing you agree to receive the Rail Construction Today weekly and the TC Media Group monthly edition. We confirm your address first. Privacy.

More from Rail Construction Today