Network Rail lines up £4m North West Christmas works ahead of Crewe and North Wales closures
Platform, drainage, signalling, overhead line and track work across the North West on Christmas Day and Boxing Day prepares for Crewe's 2027 programme, with closures to follow at Huddersfield and in North Wales.

Network Rail will spend more than £4m on upgrades across the North West this Christmas, concentrating most of the work on Christmas Day and Boxing Day and preparing Crewe for a wider programme of closures in 2027.
The infrastructure owner said on 18 November that the programme includes £1m on platforms at Crewe station ahead of roof removals in May 2027. Drainage at the station will also be diverted before track renewals in February 2027.
At Weaver Junction, just outside Crewe, teams will lay cables, clear vegetation and position materials for future power supply and signalling upgrades. Network Rail's North West route said the Crewe work formed part of a £200m investment in the hub, although its 28 October Crewe release and project page describe the programme only as a multi-million-pound investment.
Chris Wright, Network Rail North West route director, said: "It will help make the railway more resilient and reliable, while preparing the network for major improvements planned next year."
The Christmas package
Elsewhere in the region, £215k of signalling upgrades between Chester and Hooton and at Sandycroft form part of a wider £7m investment in the area, Network Rail said. A further £1m will go on overhead power line improvements between Preston and Warrington.
New sidings at Brewery Junction in East Manchester will be electrified, and £1.7m of track work at Longsight will renew 2.5km of railway on the approach to Manchester Piccadilly.
| North West Christmas work | Value |
|---|---|
| Crewe station platforms | £1m |
| Chester to Hooton and Sandycroft signalling | £215k |
| Preston to Warrington overhead line | £1m |
| Longsight track renewal | £1.7m |
The North West work sits within a £152m national Christmas investment programme, according to Network Rail's national release. Anit Chandarana, Network Rail group director, system operator, said the days between Christmas and New Year are by far the quietest of the year.
Crewe
The Christmas work is the opening stage of a longer Crewe programme. Network Rail said on 28 October that the work starts at Christmas 2026 and continues through 2027, beginning with a nine-day railway closure from 13 February.
Story Contracting is delivering the Crewe work on behalf of Network Rail, covering track, signalling and overhead line renewals, according to the project page. Network Rail said parts of the station roof and train shed also need improvement to remain fit for the future.
Tommy Fleming, Network Rail sponsor, said: "Delivering improvements on this scale will require a series of temporary railway closures, beginning at Christmas 2026."
Huddersfield and Birmingham
Passengers heading across the Pennines or to the Midlands face more disruption. The Transpennine Route Upgrade (TRU) will close Huddersfield station for 38 days from the last service on Christmas Eve until Sunday 31 January, reopening on 1 February 2027.
Network Rail said the closure would complete platform reconstruction and track realignment, increasing capacity and improving accessibility and customer facilities. Its national release describes the work as the final phase of the station's transformation, following an autumn closure of Huddersfield and Slaithwaite from 19 September to 4 October. TRU has 70 worksites along the 70-mile route and aims to halve the time lost to delays once complete.
Birmingham New Street will be affected from Thursday 24 December until Monday 28 December while engineers renew overhead wiring as part of a £13m upgrade. Network Rail said the programme replaces overhead power lines dating from the 1960s and is the first phase of a three-year programme, with further Christmas work in 2027 and 2028. During the same closure it will spend £6.4m replacing junction equipment and renewing 800 metres of track at Soho. A full timetable returns on Tuesday 29 December.
North Wales Coast
In January, the North Wales Coast Line will close for four weeks from Saturday 9 January 2027 for a programme costing more than £25m. The first three weeks affect Chester to Holyhead, Llandudno Town to Blaenau Ffestiniog and the Conwy Valley line; in the fourth week only Llandudno Junction to Holyhead stays closed. Network Rail gives the closure as running until Saturday 6 February, while Transport for Wales says the Llandudno Junction to Holyhead section will remain closed until Friday 5 February.
Network Rail said in September that the work would be delivered by rail using 22 engineering trains. It includes renewing track through the Grade I-listed Conwy Tubular Railway Bridge, where the existing track dates from 1978, and two new fully accessible footbridges at Prestatyn and Abergele to support the closure of four high-risk level crossings. Network Rail said it had reduced the Chester to Llandudno Junction closure from four weeks to three.
Transport for Wales will run limited-stop replacement buses every 30 minutes between Chester and Holyhead during the closure. It said some North Wales Coast infrastructure was receiving significant investment for the first time since the 1970s.
The first of the 2027 closures begins on 9 January, with Crewe's nine-day shutdown following from 13 February.
Sources
- Network Rail (opens in a new tab) (accessed 2026-11-18)
- Network Rail (opens in a new tab) (accessed 2026-11-18)
- Network Rail (opens in a new tab) (accessed 2026-11-18)
- Network Rail (opens in a new tab) (accessed 2026-11-18)
- Network Rail (opens in a new tab) (accessed 2026-11-18)
- Network Rail (opens in a new tab) (accessed 2026-11-18)
- Transport for Wales (opens in a new tab) (accessed 2026-11-18)
- Network Rail (opens in a new tab) (accessed 2026-11-18)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.