Network Rail to close Midland Main Line south of Bedford for 5-6 December works weekend
Track renewals at Belsize Tunnel and Sundon High Bridge, drainage at Harlington, signalling at St Albans and progress on the Luton Access for All scheme and Radlett freight interchange are planned for the weekend possession.

Network Rail will close a large section of the Midland Main Line south of Bedford on Saturday 5 and Sunday 6 December to renew track, install drainage, upgrade signalling and advance projects at Luton station and the Radlett freight interchange.
No East Midlands Railway (EMR) trains will run between London St Pancras and Bedford across the weekend, Network Rail said. Thameslink services will not run between Mill Hill Broadway and Bedford until 05.30 on Monday 7 December.
Eric Larocque, Network Rail's East Midlands operations director, said: "Carrying out these upgrades together allows us to make the most of the track access available to our colleagues, as we provide a more reliable, resilient and accessible railway for the future."
The work
Engineers will renew more than 400 metres of track at Belsize Tunnel in London and 740 metres at Sundon High Bridge, north of Luton, according to Network Rail. At Harlington in Bedfordshire, 500 metres of drainage will be installed to move water off the railway more effectively.
At St Albans in Hertfordshire, 10 renewed signalling location cabinets will be commissioned as part of work to extend the life of signals in the area.
The possession also gives time on the strategic rail freight interchange (SRFI) under construction at Radlett, Hertfordshire, where Network Rail said new points will be installed alongside cable, telecoms and signalling work. At Luton station, the Access for All project to build an accessible footbridge and three lifts will make further progress.
A run of 2026 possessions
The December closure follows two weekends in June 2026, on 20-21 and 27-28 June, when Network Rail shut the Bedford to London route and renewed 600 metres of track at Hendon and 400 metres at Belsize Tunnel. Piling and excavation for the new Luton footbridge were under way during those closures.
Track renewed in this year's closures south of Bedford, as reported by Network Rail:
| Site | Closure | Track renewed (metres) |
|---|---|---|
| Hendon | June 2026 | 600 |
| Belsize Tunnel | June 2026 | 400 |
| Belsize Tunnel | December 2026 | 400 (more than) |
| Sundon High Bridge | December 2026 | 740 |
Luton station
Network Rail started the Luton step-free access scheme in February 2026 under the Government's Access for All programme. Before the project, only platform 5 at the station had step-free access.
The bridge span was due to be installed in June 2026, with the lifts following towards the end of the year, Network Rail said when work began. Main construction was scheduled to run from February to December 2026, with the overall project planned for completion in spring 2027.
Radlett freight interchange
The Radlett works serve SEGRO Logistics Park Radlett, which SEGRO describes as the only SRFI directly serving London and the M25 region. The park spans about 1,000 acres and is planned to include 335,000 sq m of logistics warehouse space, with a 135-acre strategic rail freight interchange designed for 24 freight trains a day and operating 24 hours a day.
SEGRO said in January 2025 that it had installed a major underbridge beneath the Midland Main Line, which it called the first construction milestone on the scheme, with VolkerFitzpatrick as principal contractor. The developer said the freight terminal will be capable of operating by the time the first building on the park has been built.
Travel arrangements
EMR will run replacement buses between Bedford and Hitchin, and its tickets will be accepted on Great Northern and Thameslink services between Hitchin and London, Network Rail said.
Thameslink buses will run between Mill Hill Broadway and Luton, Luton Airport Parkway and Bedford (fast) and Luton and Bedford (all stations), with further services between Harpenden and Potters Bar via St Albans City and between Luton Airport Parkway and Hitchin via Luton.
Jenny Saunders, customer services director for Thameslink, said: "journeys will take much longer than usual for many, so we strongly advise you check what that looks like now, online, and allow plenty of extra time."
Trains between Mill Hill Broadway and Bedford are due to resume at 05.30 on Monday 7 December.
On the record: VolkerFitzpatrick
Sources
- Network Rail (opens in a new tab) (accessed 2026-11-17)
- Network Rail (opens in a new tab) (accessed 2026-11-17)
- Network Rail (opens in a new tab) (accessed 2026-11-17)
- SEGRO (opens in a new tab) (accessed 2026-11-17)
- SEGRO (opens in a new tab) (accessed 2026-11-17)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.