Weekend possessions to bed in Forest Gate and Stratford points renewals into February

Network Rail will use weekend closures between early January and mid-February 2027 to tamp and adjust eight new switches and crossings installed at Forest Gate and Stratford over Christmas, alongside rerailing, overhead line and station work.

A tamping machine working on railway track with switches and crossings
Photo: Network Rail

Network Rail will close sections of the Great Eastern main line on selected weekends between early January and mid-February 2027 to adjust and tamp eight new switches and crossings installed at Forest Gate and Stratford over Christmas.

The follow-up possessions, announced on 17 November, cover the main line between Stratford and Chelmsford, the London Overground Liberty line between Romford and Upminster, and at specific times the Southend Victoria and Southminster routes.

Network Rail said the work list includes completing the adjustment of six new switches and crossings at Forest Gate and two at Stratford station. Both sets were part of the Christmas programme announced on 22 October 2026, which scheduled a 10-day closure of the Great Eastern main line from Sunday 27 December 2026 to 3 January 2027 to renew six sets of points at Forest Gate with associated rails, sleepers and ballast, and two sets at Stratford.

Martin Beable, Chief Operating Officer for GBR Anglia, said: "This planned engineering work is very important to help maintain the safe and reliable running of the railway, and we're using this time to make sure the critical pieces of infrastructure installed at Christmas are performing as expected."

Why the second phase is needed

Network Rail said new track and the ballast beneath it settle naturally once trains start running over it. Tamping machines are then used to restore the correct track alignment, which the company said improves reliability, reduces wear and supports smoother journeys.

In its October release Network Rail described points as movable sections of rail that enable trains to change tracks.

The wider work bank

The same weekend access will be used for a tail of track, overhead line and station jobs along the route. Network Rail listed:

  • rerailing at Chadwell Heath, Brentwood, Rayleigh and Hockley;
  • refurbishment of switches and crossings at Pudding Mill Lane and Shenfield;
  • overhead line work between Romford and Chelmsford, and between Wickford and Southminster;
  • drainage work at Seven Kings;
  • vegetation clearance between Forest Gate and Ilford, alongside routine maintenance.

Station work includes roof refurbishment at Forest Gate, platform resurfacing at Manor Park, demolition of a control room at Stratford and repainting of canopies at Shenfield. Canopy repairs at Southminster and Hockley and footbridge repairs at Wickford are also listed.

Treatment trains will run across the route in the New Year carrying out leaf removal, rail cleaning, track levelling, rail grinding and ballast tamping. Network Rail said these activities reduce the impact of seasonal conditions and improve weather resilience.

The treatment fleet has been active through the autumn. On 11 November Network Rail said the trains were expected to treat an estimated 100,595 miles of track across Anglia this season, with 28,419 miles already completed, using high-pressure water jets to clear leaf residue from the rails.

Closure dates

On Saturday 9 and Saturday 16 January 2027, Greater Anglia services will not run between Ingatestone and London Liverpool Street, with rail replacement buses from Ingatestone to Newbury Park for Central line connections.

On Sundays 10, 17, 24 and 31 January and Sunday 14 February 2027, Greater Anglia services will not run between Beaulieu Park and London Liverpool Street.

On all of those dates Elizabeth line services will not operate between Liverpool Street National Rail station and Shenfield, with a reduced service between Paddington and Abbey Wood. The Liberty line will not operate, and customers are directed to bus routes 165, 248 and 370.

Beable said: "Working with our partners, a rail replacement service will run while the works take place, and passengers are advised to check before they travel and allow more time for their journey."

GBR Anglia

The announcement was issued under the GBR Anglia name. Network Rail launched the GBR Anglia unified leadership team on 14 May 2026, bringing together c2c, Greater Anglia and Network Rail Anglia in what it described as a step towards the establishment of Great British Railways. Jamie Burles leads the team as Managing Director, with Beable as Chief Operating Officer.

Network Rail said at the time there would be no immediate changes to services, branding or the way customers travel. The first GBR Anglia branded trains were unveiled on 16 July 2026, with existing c2c and Greater Anglia logos to be replaced gradually.

Network Rail's Anglia route, part of its Eastern region, covers Norfolk, Suffolk, Essex and parts of Cambridgeshire, Hertfordshire and Greater London, and employs 2,450 people.

The Christmas possession at Forest Gate and Stratford is due to start on Sunday 27 December 2026, with the first follow-up weekend closure on Saturday 9 January 2027.

Map of the UK and Ireland with a marker at Forest Gate, London
Forest Gate, London. Map: Rail Construction Today. Map credits

Sources

  1. Network Rail (opens in a new tab) (accessed 2026-11-17)
  2. Network Rail (opens in a new tab) (accessed 2026-11-17)
  3. Network Rail (opens in a new tab) (accessed 2026-11-17)
  4. c2c (opens in a new tab) (accessed 2026-11-17)
  5. Network Rail (opens in a new tab) (accessed 2026-11-17)
  6. Network Rail (opens in a new tab) (accessed 2026-11-17)

This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.

Get stories like this every Friday

The Rail Construction Today weekly: the week's railway infrastructure and construction news in one email, free, and the TC Media Group monthly edition. Unsubscribe in one click.

By subscribing you agree to receive the Rail Construction Today weekly and the TC Media Group monthly edition. We confirm your address first. Privacy.

More from Rail Construction Today