Balfour Beatty VINCI completes first half of HS2's A45 Coventry Road overbridge
HS2 Ltd says the eastbound half of the bridge that will carry the A45 over four high-speed tracks near Bickenhill is almost ready for traffic, with closures from 7 December to switch vehicles onto it.

Balfour Beatty VINCI (BBV) has finished the first half of the new Coventry Road overbridge near Bickenhill, which will carry the A45 over four HS2 tracks on the approach to Interchange station, HS2 Ltd said on 18 November.
The structure is being built in two halves so that traffic on the A45 keeps moving throughout, according to HS2. The eastbound section has taken 11 months, and HS2 said waterproofing and highway works would finish in the coming weeks before vehicles are moved onto it.
Paul Marshall, Head of Delivery at HS2 Ltd, said: "Our engineers have worked incredibly hard to develop a design solution that maintains traffic flows in each direction, while we build the bridge and excavate the ground below to make way for the new high-speed railway."
The build
HS2 said the team used a top-down method, excavating beneath the existing carriageway before installing 46 piles up to 23 metres deep and casting pile caps to carry a 2,000-tonne bridge deck.
Over the summer, 13 pre-stressed pre-cast concrete beams were lowered into position to support the 37-metre span, and 13 parapet units were fixed to the completed half, HS2 said.
Richard Husbands, Balfour Beatty VINCI's Project Manager, said: "Construction of the bridge in two halves is a complex engineering challenge, and reaching the halfway stage is an important milestone for the project."
December closures
HS2 is working with National Highways on the traffic switchover, which will move motorists onto a temporary carriageway alignment across the new eastbound section.
HS2's works notice for the A45 sets out the programme. Both carriageways will close each weeknight between 9pm and 6am from Monday 7 December until Friday 11 December 2026. A full weekend closure of both carriageways then runs from 9pm on Friday 11 December to 6am on Monday 14 December.
If the weekend closure cannot go ahead, HS2 has contingency dates of 9pm on Friday 18 December to 6am on Monday 21 December, with further weeknight closures between 14 and 19 December. The notice says fully signed diversion routes will operate during each closure and that the works are subject to consent.
Marshall said access to businesses and properties would be maintained during the closures and encouraged motorists to familiarise themselves with the diversions.
Wider scheme
The overbridge is part of a three-structure package on this stretch of the A45, between Stonebridge roundabout and M42 Junction 6, according to HS2's project page. It also includes two slip road bridges, East Way and Service Road, either side of the main road. The East Way slip road bridge and road realignment opened in May 2025, and preparatory work for the eastbound section of the main bridge started in spring 2025.
HS2's project page says traffic management during the build includes a contraflow with narrow lanes, and that the works may affect drivers on the M42, Stonebridge Island roundabout and the A452.
The bridge is one of 76 overbridges in HS2 lots N1 and N2, which VINCI valued at about £5bn when the BBV 50:50 joint venture was awarded the construction phase on 1 April 2020. The two lots cover about 90km and also include 51 viaducts and boxes, 7.5km of twin tunnel and 35 cuttings. Lot N2 runs from the Delta Junction to the West Coast Main Line tie-in.
Beneath the bridge, BBV will keep excavating the trace for the four tracks running towards Interchange station, about a mile away. HS2 says the 150-hectare Interchange site sits in a triangle of land between the M42, A45 and A452, that its construction will support 1,000 jobs, and that an automated people mover will link it to the NEC, Birmingham International and Birmingham Airport.
What happens next
BBV will start the second half of the bridge in the new year, following a similar sequence of works, HS2 said. Its project page puts construction of the westbound section at early 2027 to summer 2028.
HS2 expects the bridge to be structurally complete by the end of 2027. Permanent highway works with National Highways, covering lighting, kerbs, drainage and carriageway, will follow, with the final structure and road alignment due in use by summer 2028.
Sources
- HS2 Ltd (opens in a new tab) (accessed 2026-11-18)
- HS2 Ltd (opens in a new tab) (accessed 2026-11-18)
- HS2 Ltd (opens in a new tab) (accessed 2026-11-18)
- HS2 Ltd (opens in a new tab) (accessed 2026-11-18)
- VINCI (opens in a new tab) (accessed 2026-11-18)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.