HS2 lifts 125-tonne gantry crane into place for 18-month deck slab job on Curzon approaches
A 125-tonne gantry crane lifted on to the Lawley Middleway viaduct will place 1,516 precast slabs across the Curzon approach viaducts, in what HS2 calls the last major civils phase on the final mile into Birmingham.

HS2 Ltd is ready to begin installing precast concrete deck slabs this week on the five viaducts that carry the high-speed line into Birmingham city centre, a job it expects to take 18 months and describes as the last major phase of civil engineering on the Curzon approaches.
A 125-tonne gantry crane has been lifted on to the Lawley Middleway viaduct and engineers will begin placing slabs this week, HS2 said in an announcement on 16 November. The crane will work its way along the structures, from Lawley Middleway to Curzon 2, Curzon 1 and finally the Duddeston Junction viaduct.
According to HS2, 1,516 reinforced slabs will be placed on the viaducts to form solid decks ready for track to be laid.
Greg Sugden, HS2 Ltd's Head of Delivery for the Curzon Approaches, said: "This is a huge moment for the Curzon approaches team, as we begin what is essentially the last major phase of civil engineering works on this section of the route."
He said the decks would take about 18 months to lay, after which HS2's elevated approach into Birmingham would be structurally complete.
The slabs
The slabs are being made at Balfour Beatty VINCI's purpose-built factory at Kingsbury in Warwickshire. Balfour Beatty VINCI (BBV) is HS2's main works contractor in the West Midlands.
HS2 said the 140-strong Kingsbury team spent four years producing 2,742 segments for the Delta Junction viaducts before the production line switched to the approach slabs, keeping the local workforce in employment. BBV has separately put the Delta Junction production run at three and a half years and said the facility would be repurposed to make more than 1,200 deck slabs; HS2's figure of 1,516 is the one given in this week's release.
BBV said the Delta Junction segments together form more than four miles (6.5km) of viaduct deck.
Malik Kayatas, Section Manager at Balfour Beatty VINCI, said the crane would sit on top of the structures and "move outwards from the city centre on an 18-month journey, marking the next exciting phase of this project."
Road closures
To allow the crane to pass over Lawley Middleway while slabs are laid above the road and footways, HS2 has announced a series of temporary night-time closures of the A4540 between Garrison Circus and Curzon Circus.
A northbound-only closure will run from 10pm to 6am each night from Saturday 21 November until Sunday 6 December. Within that period the road will be shut in both directions from 10pm to 6am each night from Wednesday 25 November until Wednesday 2 December, followed by a southbound-only closure on the same hours from Thursday 3 December until Sunday 6 December.
The five viaducts
HS2's project page lists the approach as five viaducts: Duddeston Junction, Curzon 1, Curzon 2, Lawley Middleway and Curzon 3. They form the final section of elevated railway before trains reach Birmingham Curzon Street station, and use reinforced concrete decks on in-situ piers and deep piled foundations.
The 112-metre Lawley Middleway viaduct, where the crane now sits, was assembled off site. In August 2025 HS2 moved the 1,631-tonne steel structure over the ring road using a skidding system at 18 to 24 metres a night, finishing four days ahead of schedule.
Curzon 2, a 150-metre span crossing the Cross-City line near Duddeston, is described by HS2 as the tallest viaduct on the project. BBV said the 4,200-tonne bridge, with a truss of 670 steel sections, was to be slid 180 metres over three launch phases, including a closure of the Cross City line from 29 to 31 May 2026, with the tip of the arch reaching more than 40 metres once in place.
Curzon 1 crosses the River Rea between the existing railway and local businesses. Curzon 3, the last structure before the station, widens from one deck to four, spanning 65 metres at its widest as the railway splits to enter the station's seven platforms. Balfour Beatty said deck work on the first Curzon 3 sections was complete by April 2024, following a first concrete pour in November 2023. Curzon 3 is not on the gantry crane's published route.
The viaducts were designed by a joint venture of Mott MacDonald and SYSTRA with architects Weston Williamson + Partners, according to Balfour Beatty.
Duddeston Junction
The crane's final destination, Duddeston Junction viaduct, is still being launched. On 19 August 2026 HS2 said it had pushed out the first 170 metres of the structure, which it described as the first and longest of the five viaducts. HS2's project page gives its length as 375 metres while the August release describes it as 700 metres long; BBV's Ross Rendell gave 705 metres in the same release.
The launch involves seven spans crossing six railway tracks, three freight and three passenger, which John Emery, Senior Sponsor at Network Rail, said carry more than 200 passenger and freight services a day. HS2 said the next phase, crossing the passenger lines, is scheduled to begin in December 2026, with the whole operation expected to conclude in summer 2027.
On the record: Mott MacDonald, SYSTRA, Balfour Beatty
Sources
- HS2 Ltd (opens in a new tab) (accessed 2026-11-16)
- HS2 Ltd (opens in a new tab) (accessed 2026-11-16)
- HS2 Ltd (opens in a new tab) (accessed 2026-11-16)
- HS2 Ltd (opens in a new tab) (accessed 2026-11-16)
- Balfour Beatty VINCI (opens in a new tab) (accessed 2026-11-16)
- Balfour Beatty VINCI (opens in a new tab) (accessed 2026-11-16)
- Balfour Beatty (opens in a new tab) (accessed 2026-11-16)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.